Work on the project is scheduled to resume on April 8, 2024. The contractor will start on underground work on Dundee Ave. near Enterprise St. Once the underground work is complete, the contractor will install the new curb and gutter, sidewalks, and driveway aprons. Following that, the contractor will proceed to parkway restoration and completion of the new traffic signal installation. Completion of the project is anticipated to be in August.
Stay tuned to the website for future updates.
Please drive carefully through the construction zone, refrain from cell phone use, and watch for equipment and workers.