The Summit and Dundee Intersection Improvement Project is nearing completion. This project will enhance safety, improve traffic flow, replace aging infrastructure, update traffic signals, and upgrade pedestrian facilities.

Current and Upcoming Work:
Week of July 8, 2024
Pavement milling and the first asphalt layer will be placed. Next Steps: Manhole frame adjustments for final asphalt layer.

Week of July 15, 2024 (weather permitting) Nighttime Paving Operations – 8:00 PM – 6:00 AM
The final asphalt layer will be placed overnight to ensure high quality and limit daytime traffic disruptions. Message boards will be placed at both ends of Summit Street and Dundee Avenue with updates on actual paving dates.

We understand this work may cause additional noise at night and appreciate your patience and understanding. These measures ensure better pavement quality and increased safety for everyone. Stay tuned to the website for future updates.

Please drive carefully through the construction zone, refrain from cell phone use, and watch for equipment and workers.