Overall Project Construction Progress

70%
  • April 2024
    • Removal of temporary items placed for winter safety
    • Installation of western side curb
    • Storm sewer work at north end of Dundee Avenue
  • Late Spring/Early Summer 2024
    • Move to Stage 2 work on east side of Dundee Avenue
    • Complete utility installations
    • Install new curb and widen pavement
  • Summer 2024
    • Complete work on Summit Street
    • Mill and resurface Dundee Avenue and Summit Street
    • Complete permanent traffic lane markings by end of August
    • Complete traffic signal installation by September 6

Check back for future scheduling updates!