Overall Project Construction Progress
- April 2024
- Removal of temporary items placed for winter safety
- Installation of western side curb
- Storm sewer work at north end of Dundee Avenue
- Late Spring/Early Summer 2024
- Move to Stage 2 work on east side of Dundee Avenue
- Complete utility installations
- Install new curb and widen pavement
- Summer 2024
- Complete work on Summit Street
- Mill and resurface Dundee Avenue and Summit Street
- Complete permanent traffic lane markings by end of August
- Complete traffic signal installation by September 6
Check back for future scheduling updates!